Ongoing programmes and the next wave of public-sector solar. Track implementation, procurement and announcements through dated official evidence.
6programmes on the watchlistDaily review · Evidence-led status
2Implementation reported
1Procurement activity
2Announced / planning
1Status needs confirmation
6 projectsSource date and review date are shown separately
PunjabImplementation reported
CM Punjab Free Solar Panel Scheme
Punjab Energy Department
APP reported an extension through December 2026 on 13 April 2026. The department overview still carries a September 2025 completion target; current rollout totals need confirmation.
WHAT TO WATCH
Household scheme. No new application window has been verified; consult the official portal before applying.
Distribution and installation were reported continuing on 6 July 2026. The programme targets 275,000 households across 30 districts; target is not a completed-installation count.
WHAT TO WATCH
Beneficiary support and rollout monitoring. The official report states that household surveys, kits and installation carry no fee.
Pakhtunkhwa Energy Development Organization (PEDO)
PEDO lists consultant procurement entries dated 8 September 2026 for the 50% and 100% subsidized household initiatives. These entries establish procurement activity, not an open bidding window today.
WHAT TO WATCH
Consultancy and implementation monitoring. Open each tender document for submission dates, eligibility and corrigenda.
Government schools, colleges and mosque solarization
KP Energy Department / PEDO
A 31 July 2026 government briefing directed preparation of a phased solarization plan for public institutions, including schools, colleges and mosques.
WHAT TO WATCH
Planning watch. No specific open contract or rollout quantity established in this briefing.
In-principle approval and directions to start pilot work were reported on 9 January 2026. Current construction and commissioning progress have not been verified.
WHAT TO WATCH
Microgrid project watch. No open procurement or confirmed contract size established by the cited announcement.
The official project page covers tertiary hospitals, Daanish Schools, Punjab Secretariat and the CM office. Its completion target was 30 June 2026, which has passed; completion or extension is not confirmed here.
WHAT TO WATCH
Check fresh completion and procurement notices before treating this as an active supply opportunity.